Here are a few pictures of the lot pre-build. Josh and I went out this morning to take them. The excavator should be starting next Wednesday, Oct 18th, if everything goes according to plan. He thinks it should take about 1 1/2 days to excavate the basement and garage. The basement will only be excavated about 4'4", so that we can avoid window wells. The basement should go in the following week. We ordered a package from Viceroy, which will supply everything but shingles, to get us to lock-up. This package has been confirmed for delivery on Nov 2nd. My dad (Ron) and anyone else who wants to help (hint, hint!!) will start framing Nov 3rd!!!