Yesterday was another busy day. The gravel for the weeping tile was put in, so then we were able to get the foundation inspection done. Todd and Dad ran into a little snag when they found out that one lift of sheeting (for the sub floor) was factory defect, so the tongue was off and wouldn't fit properly in the groove. They (the floor system group) is supposed to be dropping off another lift this morning. All the floor joists and beams are up, and the rim boards around the outside just need to be put in place. Todd started to backfill around the house last night and will continue to get some more done today. This will make it much easier to work around the house.